Lawrence Berkeley National Laboratory - Building 33
This is a new research facility at LBNL. It has three stories with rooftop mechanical equipment and a remote central plant that required coordination of underground trenching with other trades. We installed an Automated Logic control system for Airco Mechanical to control the following mechanical equipment:
·      4 air handlers
·      19 exhaust fans
·      6 blowers
·      6 AC units
·      12 pumps
·      2 boilers
·      1 heat exchanger
·      2 chillers
·      2 cooling towers
·      121 VAV’s
·      16 fume hoods
This was a challenging but successful project.